Lourtier (vs): fregnoley fuse bridge:
Keystone-SDA
Fifteen days after the commissioning of a provisional bridge belonging to the army. Therefore, making it possible to link Champsec to Lourtier and the Haut Val de Bagnes, the work in the Torrent du Fregnoley area continues to move forward. Furthermore, The fuse bridge is again operational. Furthermore, – Lourtier (vs): fregnoley fuse bridge
(Keystone-ATS) The fuse bridge destroyed by a torrential lava on June 2 was put back in service. Therefore, A new carpet was placed in the same place. Nevertheless, The army lourtier (vs): fregnoley fuse bridge having put a service a bridge until November 30, the work is only used for the site. Therefore, “Last week. four small torrential lavas still descended from the mountain, but they passed under the fuse bridge,” reveals Pierre-Martin Moulin, secretary general of the town of Val de Bagnes.
For several months. the municipal authorities of Val de Bagnes and the State of Valais have planned to inaugurate a gallery of 70 meters allowing motorists to cross, in all times, the Bed of the Torrent du Fregnoley. Despite the damage recorded in the sector since last June, linked to various torrential lavas, the established timing remains current.
Still for December 2025
“We always hope to be able to inaugurate it in December,” confirms Piere-Martin Moulin. “This week, the last micropiles will be installed. In early August, we will start the concreting part. »»
The construction of the 40. 000 cubic meter dumping ground, planned lourtier (vs): fregnoley fuse bridge upstream from the Torrent bed, should be completed at the end of the week. The book will reduce the impact of future torrential lavas. In total, a dozen site machines, including excavators, are active in the sector.
Three axes are better than
Last file in progress: the construction of a road on the left bank. downstream from the Torrent bed. Access allowing the loggers to deforest the sector are under construction.
At the same time. the calculations of the costs of carrying out the road, the construction and the installation of a bridge 30 meters long and the security works are in progress. “Once these calculations are finalized and checked, they will be subject to the municipal council for validation and adjudication. We are talking about a period of auction within a month approximately, ”sums up Pierre-Martin Moulin. “We hope to put this route into service when the army bridge is no lourtier (vs): fregnoley fuse bridge longer accessible. »»
Between the road axis taking the fuse bridge. the future gallery and a road on the left bank, the authorities want to give themselves a maximum of advantages so as not to see Lurtier and the high val de Bagnes be cut off from the world in 2026 for a third consecutive year.
Further reading: Switzerland: an elected official wants to remove the prison for small fines – An aggressive bull “out of control” in French -speaking Switzerland – Animal well-being: Switzerland is struggling to strengthen its legislation – More capital invested in Swiss start-ups – Geneva is adorned with red and white for the Swiss match against Finland – Rts.ch.