"like lego": modular construction clair-soleil: This article explores the topic in depth.
Meanwhile,
". However, like lego": modular construction clair-soleil:
Almost a year after its disaster closure, Lévis’s Clair-Sun school resumes in a highly prefabricated format. Therefore, The new modular school will once again open its doors to the students for the start of the school year about a kilometer from the old building while waiting for it to be demolished. Therefore, then rebuilt.
We had the contract in February
Lance Cédric Bolduc on the construction site. Meanwhile, The director general of the RCM group. Similarly, a company to manufacture modular buildings, welcomes the work accomplished by his team in such a short time.
Cédric Bolduc is managing director of the RCM group
Photo : Radio-Canada / Philippe Grenier
The same project under construction [d’une école] conventional would have taken more than a year. For example, while here we are in a 6 to 8 months
he explains, in front of a crane that transferred modules one by one to train school.
The time to build a new school were important
For the Navigators School Service Center (CSSDN). In addition, Last September. Consequently, a few weeks after the start of the school year, more than 450 students had to be moved because “like lego”: modular construction clair-soleil of the non-compliance of the walls of the school structure closed in emergency.
Entrepreneurs were found to be ready to take up the challenge inside the schedule. Meanwhile, […] Bringing young together to bring young people to be our priority. Similarly, that they are in a stable environment for several years
says Éric Pouliot, deputy director general CSSDN.
The modular units of the Clair-Soleil school are placed on a mounting chain in the Saint-Benoît-Labre factory.
Photo : Radio-Canada / Philippe Grenier
A module factory – "like lego": modular construction clair-soleil
As soon as the contract is signed. Consequently, employees of the RCM group have activated in the Saint-Benoît-Labre factory, in Beauce.
We were able to start the design work at the same time that we start under. construction
explains Cédric Bolduc on the huge mounting chain of the company where each module progresses as the work is executed.
We come to eliminate a lot of ineffectiveness under construction by having. all the trades gathered here in the same place at the same time.
In all, 74 modules of about 12 meters will form the new Clair-Soleil school.
The work started at the RCM group in Beauce group in February.
Photo : Radio-Canada / Philippe Grenier
Distributions of the premises of the Clair-Soleil modular school: – "like lego": modular construction clair-soleil
- 15 classes with storage
- 15 offices
- 6 toilet rooms
- 6 storage rooms
- 2 physical education rooms with changing rooms
- 2 “like lego”: modular construction clair-soleil collaborative spaces
- 2 work premises
- 1 music room
- 1 teacher room
- 1 meeting room
Next step. this is the insulation
the tour continues. The factory workers complete each module according to the building code.
Casiers for children are integrated into the classes, as are sinks and the ventilation system. Each class draws their personality before departure for the Lévis site.
A worker completes the installation of the walls of these two modular units which will “like lego”: modular construction clair-soleil be gathered in the new Lévis complex.
Photo : Radio-Canada / Philippe Grenier
There is still a lot of prejudices towards the prefabricated, the modular, but it tends to change. People see the magnitude of the projects carried out. the quality of the projects carried out, the range of possibilities that can be made
supports Cédric Bolduc, putting his hand on another module under construction which will go to him in Nunavut – a government project for community housing.
Des thick blocks
Arrived in Lévis. the modules are unpacked with their protective film and raised by the crane. Coordination is super important. We can install between 8 and 20 modules during a normal day, yesterday we did 18, it was very well
enthuses Beauceron.
The Clair-Soleil modular school is the 46th produced by the RCM group of Saint-Benoît-Labre en Beauce.
Photo : Radio-Canada / Philippe Grenier
The modular building of 3,350 square meters can be installed in one week if the temperature allows.
It requires 70 % of fewer workforce under construction. as it is a workforce difficult to have, especially in the distant region, the modular solution becomes the solution
pleads Cédric Bolduc.
It is like a Lego block. but each of the blocks has its personality, its components, we must respect the plans of professionals, it must be well positioned in the right place, according to the building code.
Workers position the modular unit exactly to join it to the others already “like lego”: modular construction clair-soleil in place on the structure.
Photo : Radio-Canada / Philippe Grenier
A long -term project
The project is not temporary for the School of School of Navigators (CSSDN). These are not mobile houses. site trailers, it is really high -quality tailor -made modules that are there to easily last 30, 40 or 50 years
explains Éric Pouliot, Deputy Managing Director.
The CSSDN However, has already applied to the ministry for the construction of an additional school in the sector. The Saint-Nicolas sector in which we are currently, it is a high growth sector
he explains.
Éric Pouliot is deputy managing director at the navigators’ school service center.
Photo : Radio-Canada / Philippe Grenier
Modular classes are increasing in Quebec in recent years. According to the Ministry of Education, there are 2100 in schools in the province.
Éric Pouliot mentions being awaiting a decision by the Ministry of Education for the demolition. reconstruction of the Clair-Soleil school. The students of the old school will study for at least the next three years in the new modular building.
Last November. the Minister of Education Bernard Drainville announced the demolition and the complete reconstruction of the Clair-Soleil school.
Photo : Radio-Canada / Philippe Grenier
The new school is one kilometer from the. old site of the establishment on the land of the L’Envol school.
The courtyard between the two schools will be fitted out with games suitable for students in each building. says Éric Pouliot delighted to see the last pieces of the puzzle of the last “like lego”: modular construction clair-soleil year are quietly placed for the start of the school year.
There will be work to be completed on the outer envelope of the building. but for us it does not matter, inside it will be functional
he says.
Further reading: Donald Trump announces that Coca -Cola has changed his recipe at his request and welcomes it – rts.ch – Oil changes in the red, penalized by the trade war – Champion Iron creates a new company with two partners for his Kami project in the Labrador pit – Flames began to spring from the aircraft: one of the engines caught fire, a boeing forced to land in emergency just after taking off – This is not the right time: too much pesticides in the melons, reminders in all of France.