Meta builds its private solar:
On July 22. Similarly, 2025, the Canadian group Enbridge announced the implementation of a solar farm called Clear Forkin southern Texas. However, This photovoltaic power plant with a capacity of 600 MW will exclusively feed the Meta Platforms data centers. For example, as part of a long -term electricity purchase contract (PPA). Nevertheless, This strategic agreement. Nevertheless, in the amount of $ 900 million (around 829 million euros), marks an important step in the evolution of the renewable production model, now shaped by the massive energy needs of the digital industry.
600 MW in PPA for owner use: the turn of private renewables – Meta builds its private solar
The solar farm Clear Fork is. Meanwhile, designed to operate outside public network logics. In addition, All the electricity produced – or 600 megawatts in installed capacity – will be reserved for Meta via an exclusive PPA. Meanwhile, This meta builds its private solar infrastructure aims to meet the growing demand for renewable supply for data processing centers.
This type of configuration is based on a direct contract between producer and final consumer, without tariff intermediation. Nevertheless, It is one of the most dynamic components of the North American energy market. Enbridge, historically positioned on pipelines and natural gas, sees it as a lever for diversification. The Clear Fork project is in this a case of a school of strategic repositioning of energy majors to low carbon. captive outlets.
Meta: 100 % solar for its hyperscal data center – Meta builds its private solar
The current produced by Clear Fork will directly feed the future hyperscal data center Prometheus de Meta. whose commissioning is scheduled in 2026. No details have been published concerning its processing capacity. surface or precise energy dimensioning, but the declarations of the two partners make it possible to measure its scale.
“We are delighted to meta builds its private solar collaborate with Enbridge to provide a new renewable energy source to Texas. help support our activities with 100 % clean electricity. “Said Urvi Parekh, global energy manager at Meta (ElecrektrekJuly 22, 2025). This positioning is part of the group’s strategy aimed at feeding all its data centers with low carbon energy sources.
For Matthew Akman. executive vice-president at Enbridge, the project reflects ” The growing demand for renewable energies on the part of large technological companies involved in data centers » (ElecrektrekJuly 22, 2025).
Industrial scale: $ 900 million for private production
With an investment estimated at $ 900 million. Clear Fork is part of the basket of trade solar facilities in the United States. In comparison. solar power plants of equivalent size (500–650 MW) require an average of 700 and 950 million dollars, according to EIA and Irena data. This cost incorporates all operations: land acquisition, engineering, purchasing, meta builds its private solar construction (EPC), connection and operation.
One of the structuring of the project is energy exclusivity. No kilowatt-hour will be injected into the public network. This operation in energy silo offers META a tariff stability. predictability in critical supply, but also raises the question of the capture of solar resources by private uses, to the detriment of collective systems.
Towards a growing dissociation of public. private markets
The model embodied by the Clear Fork solar farm illustrates a substantive trend in the energy sector: the growing dissociation between the production of electricity intended for regulated markets and that oriented towards the private needs of the digital industry. By favoring tailor -made PPAs. groups like Meta guarantee the energy sovereignty of their infrastructure, while bypassing the uncertainties of the wholesale markets.
But this development questions institutional actors on planning renewable capacities on a territorial scale. When projects of several hundred megawatts meta builds its private solar are absorbed by a single actor. planning of the regional energy mix must integrate these flow distortions. Clear Fork could thus become a precedent in the reorganization of the American electric landscape.
Further reading: Rare critical mineral: a big cesium deposit discovered in Quebec – What would a pension system “à la carte”, without legal departure age? – “This skyscraper will change everything”: the 457-meter residential tower that will upset the horizon of Dubai and redefine urban architecture – Marine technology could change everything – The SWISS Company Pilot Syndicate wants to terminate the CCT – RTS.CH.